back

Provision/Installation Of 500Kva Transformer At Gambari In Ogo-Oluwa/Surulere Fed. Constituency, Oyo State

folder

Provision/Installation Of 500Kva Transformer At Gambari In Ogo-Oluwa/Surulere Fed. Constituency, Oyo State

-

eyemarked

-

REVIEWS

-

AVG. SENTIMENT

 Installation Of 1 X No. 500Kva, 33/0.415Kv Transformer (Copper To Copper) With Accessories  Stringing Of 0.35Km Of 150Mm2 Lt, Aac (Route Length) Ni...

SUPERVISING MDA

Provision/Installation Of 500Kva Transformer At Gambari In
Ogo-Oluwa/Surulere Fed. Constituency, Oyo State

NATIONAL RURAL ELECTRIFICATION AGENCY

OYO

STATES

ERGP15871968

project CODE

SECTOR

FEDERAL MINISTRY OF WORKS

MINISTRY

-

DEPARTMENT

Completed

PROJECT STATUS

100%

completed

page-views

248

PAGE VIEWS

Eyemark

-

PROJECT TIMELINE

Eyemark

28th Nov 2019

START DATE

Eyemark

-

END DATE

children

None

CHILDREN PROJECT

Project Description

Below explains what this project is all about.

 Installation Of 1 X No. 500Kva, 33/0.415Kv Transformer (Copper To Copper) With Accessories  Stringing Of 0.35Km Of 150Mm2 Lt, Aac (Route Length) Nigeria Cable  Erection Of 2 Nos. 10.36M Ht Poles  Erection Of 8 Nos. 8.5M Lt Poles

Contractors

Below are the contractors working on this project.

Sustainable Development Goals (0)

Below are the Sustainable Development Goals this project targets.

Project Location 1

Project Reviews

view all

general sentiment

No reviews yet

positive

sentiment

0

neutral

sentiment

0

negative

sentiment

0

avatarprofile harmburger

New to ,Eyemark,?

Sign up now to keep projects within your supervision!

By signing up, you agree to the Terms of Service and Privacy Policy, including Cookie Use.