Expansion Of Existing Gat Apron At The Malam Aminu Kano International
3
eyemarked
-
REVIEWS
-
AVG. SENTIMENT
Expansion Of Existing Gat Apron At The Malam Aminu Kano International
SUPERVISING MDA
FEDERAL MINISTRY OF AVIATION HQRTS
KANO & 1 more
STATES
•
ERGP31141630
project CODE
•
SECTOR
•
FEDERAL MINISTRY OF AVIATION
MINISTRY
•
-
DEPARTMENT
Ongoing
PROJECT STATUS
15%
completed
₦1.06B
TOTAL PROJECT COST
6 Months
PROJECT TIMELINE
2nd May 2022
START DATE
1st Dec 2022
END DATE
₦1.21B
TOTAL APPROPRIATED
₦317.73M
AMOUNT SPENT SO FAR
None
CHILDREN PROJECT
1.03K
PAGE VIEWS
Below explains what this project is all about.
Contractors
Below are the contractors working on this project.
Sustainable Development Goals (0)
Below are the Sustainable Development Goals this project targets.
Project Location 2
Project Reviews
general sentiment
No reviews yet
positive
0
neutral
0
negative
0
Project Updates (1)
Project Update On Expansion Of Existing Gat Apron At The Malam Aminu Kano International
These are some of the results of the monitoring and evaluation exercise done on Expansion Of Existing Gat Apron At The Malam Aminu Kano International as at 1st August, 2022
0
0
0
0 Comments
Be the first to review this
Discover
Categories
New to Eyemark?
Sign up now to keep projects within your supervision!
By signing up, you agree to the Terms of Service and Privacy Policy, including Cookie Use.